Programme update: November 2019

By on

This programme update relates to the period of 25th November – 6th December.

Current works:

  • Demolition of existing basement and foundations.
  • Erecting site hoarding John Street.
  • Site clearance.
  • Exploratory works.
  • Sound monitoring.
  • Dust monitoring.

A two week look ahead:

  • Crusher on site – crushing concrete for 5 days
  • Commencing foundations for crane bases
  • Reduce level dig on high level in block E – White Street
  • Sound monitoring
  • Dust monitoring
  • Erecting site hoarding – Edward Street
  • Installing privacy screen