Planned Works

Revised Construction Delivery Programme for 2022

Unfortunately  the original construction programme was severely impacted by the Coronavirus pandemic meaning the original completion quickly became unachievable. Over the course of 2021 McLaren Construction worked with First Base and Patron Capital to devise new completion dates for the differing elements of the building. 

The new delivery dates see the first residential buildings completed for June 2022 with the final section ready for August of 2022.

Commercial office buildings will be offered for occupiers fit out from July of 2022 with all external access roads, pavements and landscaped areas completed by early Autumn of 2022.

The new completion dates are shown on the summary chart below.

Check back for regular progress updates throughout the course of 2022

Revised works programme 2022