News

Tuesday 02nd June

 

Due to an obstruction being found in the existing slab located near the Job centre building earlier today, we will need to carry out disruptive works today in order to remove it. Therefore between the hours of 11am & 2pm today there will be noisy works being undertaken, this will involve the use of breaking and…

Continue reading

Friday 29th May

 

Please note that we intend to carry out drilling and breaking works to the south west corner of the site today (adjacent to the Job centre building) Between the hours of 1100 – 1400 there will be some disruption which will include noise and vibration, control measures will be in place to minimise where possible.…

Continue reading

Thursday 28th May

 

Please note that in order to remove an underground obstruction we shall be undertaking noisy works to break up the slab area adjacent to the Job centre building on John Street These works will take place between 1000-1200 & 1400-1600 today. Apologies for any disruption this may cause.

Site Activity – 20/05/20

 

Please  note that we shall be undertaking drilling and below ground works at the corner of Edward St & White St between the hours of 1000am to 1400pm. We apologise for any disruption this may cause.

Site activity / 16th May 20

 

Please note that on Saturday 16th May 2020 , we shall have a small number of operatives on site. Our works will require the use of 1no Tower crane and approx. 10-15 operatives who will only be using hand tools. We shall not be using mechanical plant and no noisy works will be undertaken.

Planned works

 

Please note that due to a mechanical failure on one of our Tower Cranes we have had to use an alternative method of placing concrete. This has involved a concrete lorry being reversed onto site via the corner of White Street and Edward Street. Unfortunately this delay will mean that site will not be closed…

Continue reading

Planned works / Breaking of slab

 

Further to our previous post in relation to the planned works to break out the obstructions under the concrete slab today and tomorrow, we are able to inform you that this phase of works were completed at 1405pm today. Therefore we shall not be needing to break out any further areas either for the remainder…

Continue reading

Planned works / Update

 

As you are aware we have continued working on the Edward Street Quarter scheme over the past 7 weeks, albeit at a much reduced capacity in order to align with the Safe Operating procedures laid out by the Government. This week has also seen the original restrictions and guidelines partially lifted. During this period, we…

Continue reading

Programme update: drilling works

 

We apologise for the delay in drilling works, which have overrun by a couple of weeks than originally planned. The drilling work has been to remove further obstructions from the ground that had not been identified previously and as such, mean they have to be removed to allow column bases to be installed which are…

Continue reading

COVID-19 update – Construction work

 

The health, safety and wellbeing of our customers, colleagues, supply chain partners and the wider public is our top priority. Our focus is on the safe continuity of business during this period and we will continue to review our solutions as the situation evolves. We are having regular conversations with our customer, First Base, and…

Continue reading